New project for David Lloyd in Ipswich

Posted By :
Comments : Off

DL Ipswich started on site 13th May and is a fast track scheme for a duration of 6 weeks. All works will carried out whilst maintaining a fully operation facility for the client.

Works include the refurbishment and re-brand of the bar area to a new Dlcious bar/restaurant inclusive of new private adult meeting room area and DL kids playzone. On the first floor works will also include conversion of existing studio to new branded spin and creation of new mind and body studio to first floor and refurbishment existing first floor bar. Refresh of the poolhall and reception will also be carried out during the works.

We have now handed over Phase 1 New Spinning Room and Dlcious, and have now taken possession of additional area’s for the remaining 4 weeks of the programme.

DL_Ipswich_phase1