SLM Paddington Community Suite extension now complete

We have now completed our 19 week project for SLM at Paddington, which consisted of the design and build of a 175m² single storey rear extension to the existing pavilion gym. The works included an internal fit-out and M&E services to provide a new Community Suite facility to...
07
OCT
2019

Works progressing well at South Oxhey Leisure Centre

Works are progressing well at South Oxhey Leisure Centre with the main structure and the erection of the steel frame nearing completion. Internal groundworks are also moving along with the formation of both the main and learner pools and the brickwork has now commenced. The...
02
MAY
2019

Successful handover at Dormers Wells Leisure Centre

We are pleased to announce the successful handover of the refurbishment works to the SLM Dormers Wells Leisure Centre. The project consisted of a refresh to the ground and first floor studios, the Dance studio and the creation of a new staff room and office. The fast-track...
09
APR
2019

Works starting at SLM Paddington

We are delighted to announce that we are about to start works to the SLM Paddington Recreation Ground community studio extension. The 175m2 development commences on the 15th April 2019 with a 20 week construction programme. The scheme will be adding to the existing quality...
01
FEB
2019

Works progressing well at SLM Bracknell

Works are progressing well at SLM Bracknell, with the dry changing areas, reception, Village Change phase 1 and the large fitness suite (850sqm floor area) all handed over prior to the Christmas break. We are currently working on phase 2 of the Village Change, the café...
24
JAN
2019

South Oxhey Leisure Centre extension

We are delighted to confirm that the works to extend the South Oxhey Leisure Centre are due to start in the next few weeks. Gareth Bush is our VincentStokes site based Project Manager for the works and has been based at the site for 3 months, planning the works and completing the...
23
OCT
2018

Taro Leisure Centre nearing completion…

We are nearing completion of the 36 week SLM Taro leisure centre refurbishment project! A £2,000,000 scheme including the demolition of the existing single storey building which housed the reception area and the construction of a new 2 storey extension which will contain the new...
05
FEB
2018

Works at Seymour successfully handed over

Our refurbishment works at Seymour Leisure Centre are now complete and open to the public. The project included the refurbishment of the wet and dry changing rooms, the gym, spa area, the creation of a new dance studio in the basement, a new spin studio and improvements to the...
20
JUN
2017

Progress at Central Park

Work is progressing well on our latest project for SLM at Central Park. We are now 8 weeks in to a 24 week programme and everything is on track. The client is delighted with how the project is being managed and very pleased with progress to date.
19
MAY
2017

Project starts at Paddington Recreation Ground

Our new 12 week project for SLM at Paddington Recreation ground has now started, with the initial strip out of the gym and changing facilities. When completed the facility will have a new gym, with upgraded changing rooms. Watch this space for photos of the competed project.