We are now 14 weeks into our 45 week program at SLM Parklands, Oadby and are currently working on the new swimming pool, plant rooms, new retail space, café area, changing rooms and new reception area.
So far completed are; live services, internal area strip out, pool steel frame work erected, culvert diversion and the ring beam has been poured and completed.
Last week the ground workers also got the blinding completed, so this week they will be starting the formwork for the pool and the filtration tanks, with insulation and concrete to follow.
Watch this space for regular updates on the project.