Works at Peckham Pulse proceeding well

Posted By :
Comments : Off

Phase 1 works at Peckham pulse are nearing an end, with the Reception, Soft Play, Changing rooms, Fitness and Spin studios – all handed over, and the first floor fitness suite due to complete by 17th February.

For phase 2 the works will start with the Village- a 12 week programme, with handover due 15th May.

Mark Leahy of SLM and the local council are very pleased with progress and quality. This has led to further negotiated work in the Southwark area.